Full Schedule for BART Path Work Now Set in El Cerrito
BART has released the complete anticipated schedule for reconstruction of the Ohlone Greenway, showing the timeframe of the x segments in El Cerrito.
Here’s the full schedule from BART showing anticipated start and completion dates for reconstruction for various sections of the Ohlone Greenway, commonly known as “the BART path.” The transit agency needs to do seismic reinforcement of its elevated tracks that run above the Greenway, and in cooperation with the City of El Cerrito, it is also combining the existing two paved paths, which were originally intended as separate paths for bicycles and pedestrians, into a single, wider multi-use path. The work is projected to begin in January 2012 and be finished in January 2013.
Ohlone Greenway Closings
Start Date
Find out what's happening in El Cerritowith free, real-time updates from Patch.
Finish Date
Cutting Blvd. 1o San Pablo Ave.
Find out what's happening in El Cerritowith free, real-time updates from Patch.
Jan. 2012
Aug. 2012
Brighton Ave. to Fairmount Ave.
Jan. 2012
Sept. 2012
Potrero Ave. to Hill St.
Feb. 2012
Aug.. 2013
Central Ave. to Stockton Ave.
June 2012
Feb. 2013
Portola Ave. to Manila Ave.
Aug. 2012
Mar. 2013
Stockton Ave. to Portola Ave.
Jan. 2013
Sept. 2013
Manila Ave. to Potrero Ave.
Jan. 2013
Sept. 2013
For the full list showing Albany and Berkeley segments too, please see the attached BART information sheet.
More information about BART’s earthquake safety program is available on the BART web site. Those who wish to contact BART about the program can email earthquakesafety@bart.gov or call 510-412-5546.